13-08-24
Scheduled work on electrical equipment in the Tsvetochnaya-2 data center (SPB-2)
from
13-08-24 23:00 MSK
to
14-08-24 09:00 MSK
|
13-08-24
Scheduled works on electrical equipment in data center Dubrovka-2
from
13-08-24 09:30 MSK
to
13-08-24 18:00 MSK
|
12-08-24
Scheduled works on electrical equipment in data center Dubrovka-2
from
12-08-24 09:30 MSK
to
12-08-24 18:00 MSK
|
09-08-24
Scheduled work on electrical equipment in the Dubrovka-2 data center
from
09-08-24 09:30 MSK
to
09-08-24 18:00 MSK
|
08-08-24
Planned work on infrastructure modernization in the ru-9 Cloud Platform pool
from
08-08-24 21:00 MSK
to
08-08-24 23:59 MSK
|
08-08-24
Scheduled work on electrical equipment in the Dubrovka-2 data center
from
08-08-24 09:30 MSK
to
08-08-24 18:00 MSK
|
08-08-24
Planned work on the modernization of server equipment in SPB-2
from
08-08-24 00:00 MSK
to
08-08-24 07:00 MSK
|
07-08-24
Scheduled work on electrical equipment (Berzarina-1)
from
07-08-24 21:00 MSK
to
08-08-24 06:00 MSK
|
07-08-24
Problems when creating virtual machines in the ru-1c location.
|
07-08-24
Planned works on electrical equipment in data center Dubrovka-2
from
07-08-24 09:30 MSK
to
07-08-24 18:00 MSK
|
07-08-24
Planned works on electrical equipment in data center Dubrovka-2 31.07.24
from
07-08-24 09:30 MSK
to
07-08-24 18:00 MSK
|
07-08-24
Planned work to modernize the infrastructure in the Berzarina-1 data center
from
07-08-24 00:00 MSK
to
07-08-24 04:00 MSK
|
06-08-24
Scheduled work on electrical equipment in the Dubrovka-2 data center
from
06-08-24 09:30 MSK
to
06-08-24 18:00 MSK
|
06-08-24
Planned infrastructure upgrade works in data center “Dubrovka-1” SPB-4 06.08.24
from
06-08-24 00:00 MSK
to
06-08-24 08:00 MSK
|
06-08-24
Planned work on the modernization of server equipment in SPB-2
from
06-08-24 00:00 MSK
to
06-08-24 07:00 MSK
|
06-08-24
Planned work on the VMware public cloud infrastructure in the regions: SPB and MSK
from
06-08-24 00:00 MSK
to
06-08-24 04:00 MSK
|
05-08-24
Scheduled work in the VMware public cloud
from
05-08-24 11:00 MSK
to
05-08-24 14:00 MSK
|
05-08-24
Planned infrastructure upgrades for the CRaaS service
from
05-08-24 10:00 MSK
to
05-08-24 19:00 MSK
|
05-08-24
Planned works on electrical equipment in data center Dubrovka-2
from
05-08-24 09:30 MSK
to
05-08-24 18:00 MSK
|
02-08-24
Planned works on electrical equipment in data center Dubrovka-2
from
02-08-24 09:30 MSK
to
02-08-24 18:00 MSK
|
01-08-24
Planned works in locations SPB-4 and SPB-5
from
01-08-24 13:00 MSK
to
01-08-24 20:00 MSK
|
01-08-24
Planned works on electrical equipment in data center Dubrovka-2
from
01-08-24 09:30 MSK
to
01-08-24 18:00 MSK
|
30-07-24
Extension of emergency work in the gis-1 Cloud Platform region
from
30-07-24 16:00 MSK
to
30-07-24 18:00 MSK
|
30-07-24
Planned work on updating load balancers in the ru-2
from
30-07-24 16:00 MSK
to
30-07-24 20:00 MSK
|
30-07-24
Emergency work in the gis-1 region of the Cloud Platform
from
30-07-24 14:00 MSK
to
30-07-24 16:00 MSK
|
30-07-24
Scheduled work SPB-3
from
30-07-24 09:30 MSK
to
30-07-24 18:00 MSK
|
30-07-24
Planned works on electrical equipment in data center Dubrovka-2 30.07.24
from
30-07-24 09:30 MSK
to
30-07-24 18:00 MSK
|
30-07-24
Planned work on the modernization of server equipment in SPB-2
from
30-07-24 00:00 MSK
to
30-07-24 07:00 MSK
|
29-07-24
Planned work to improve the stability of the control panel for dedicated servers
from
29-07-24 23:00 MSK
to
30-07-24 00:00 MSK
|
29-07-24
Problems in the Mail Service section
|
29-07-24
Unavailability of creating virtual machines with a public address of the Cloud platform in the gis-1 pool
|
29-07-24
Planned works on electrical equipment in data center Dubrovka-2 29.07.24
from
29-07-24 09:30 MSK
to
29-07-24 18:00 MSK
|
27-07-24
Control panel malfunction
|
26-07-24
Planned works on infrastructure modernization in the data center "Tsvetochnaya-1"
from
26-07-24 00:00 MSK
to
26-07-24 00:10 MSK
|
25-07-24
Planned work on upgrading the infrastructure for DBaaS maintenance in the KZ-1 pool, 07/25/2024
from
25-07-24 15:00 MSK
to
25-07-24 17:00 MSK
|
25-07-24
Planned infrastructure modernization works for the Managed Kubernetes service in the kz-1 pool, 07/25/2024
from
25-07-24 15:00 MSK
to
25-07-24 17:00 MSK
|
25-07-24
Planned work on upgrading the infrastructure for CRaaS
from
25-07-24 11:00 MSK
to
26-07-24 02:00 MSK
|
23-07-24
Network loading of dedicated servers in MSK and SPB
|
22-07-24
Planned work on wireless routers in gis-1 (Cloud)
from
22-07-24 23:00 MSK
to
22-07-24 23:40 MSK
|
22-07-24
Inaccessibility of the mobile farm section in the control panel
|
22-07-24
Transfer of planned work on migration of ru-9a from 07/15/2024 to 07/22/2024
from
22-07-24 19:00 MSK
to
22-07-24 21:00 MSK
|
19-07-24
Planned work to modernize infrastructure in location ru-8 07/19/2024
from
19-07-24 14:00 MSK
to
19-07-24 15:00 MSK
|
19-07-24
Planned work to modernize infrastructure in location ru-9 07/19/2024
from
19-07-24 12:00 MSK
to
19-07-24 13:00 MSK
|
19-07-24
Planned work on power supply to the racks of the Berzarina DC 07/19/2024
from
19-07-24 10:00 MSK
to
19-07-24 11:00 MSK
|
19-07-24
Scheduled maintenance on the modernization of infrastructure in the data center "Dubrovka-1" SPB-5
from
19-07-24 00:00 MSK
to
19-07-24 06:00 MSK
|
18-07-24
Scheduled maintenance of service resources, 18.07.24
from
18-07-24 21:00 MSK
to
18-07-24 23:00 MSK
|
18-07-24
Scheduled work on network equipment MSK-2, 07/18/2024
from
18-07-24 11:00 MSK
to
18-07-24 13:00 MSK
|
17-07-24
(CDN) Operations with CDN-connected objects are limited
|
17-07-24
Planned work to modernize the Cloud platform network infrastructure in location kz-1a
from
17-07-24 22:00 MSK
to
17-07-24 23:50 MSK
|
17-07-24
Planned works on infrastructure modernization in the data center "Dubrovka-3" SPB-3
from
17-07-24 10:00 MSK
to
17-07-24 18:00 MSK
|