Work to upgrade the power supply system, involving the disconnection of one power feed, is scheduled at the Tsvetochnaya-2 site starting at 10:00 (UTC+3) on November 16, 2026, and continuing until completion.

During the work, equipment with two power supplies will be powered by the second feed. Equipment with a single power supply will be switched to the active feed if the rack is equipped with an automatic transfer switch (ATS).

No server shutdowns are planned during the work.