Scheduled maintenance on MSK-6 electrical equipment from 27-10-26 09:00 MSK to 27-10-26 13:00 MSK

Scheduled maintenance Bare Metal Pools MSK-6
27-10-26 09:00 MSK · 4 hours

Updates

Scheduled

On October 27, 2026, from 09:00 to 13:00, annual maintenance will be performed on transformer T-8, located at MSK-6. To carry out the work safely, transformer T-8 will be taken out of service and placed in maintenance mode.

During the T-8 transformer’s ТО-12 maintenance, electrical switchboard No. 8 will be supplied by diesel generator set 8 through an uninterruptible power supply (UPS). The UPS has a battery runtime of 41 minutes. Transformer T-8 takes 15 minutes to switch on.

This work is not expected to interrupt service; it will only reduce redundancy.