Scheduled maintenance on electrical equipment at MSK-6 from 26-10-26 09:00 MSK to 26-10-26 13:00 MSK

Scheduled maintenance Bare Metal Pools MSK-6
26-10-26 09:00 MSK · 4 hours

Updates

Scheduled

On 26 October 2026, between 09:00 and 13:00, annual maintenance will be carried out on transformer T-7, installed at MSK-6.

To perform the work safely, transformer T-7 will be taken out of service.

During the T-7 transformer’s TO-12 maintenance, electrical panel No. 7 will be supplied by diesel generator set 7 via an uninterruptible power supply (UPS). The UPS has a runtime of 28 minutes. Transformer T-7 takes 15 minutes to switch on.

This work is not expected to interrupt service; it will only reduce redundancy.