Planned maintenance work on the electrical equipment of MSK‑6, machine hall No. 2 from 08-10-26 13:00 MSK to 08-10-26 16:00 MSK

Scheduled maintenance Bare Metal Pools MSK-6 Services Dedicated Servers
08-10-26 13:00 MSK · 3 hours

Updates

Scheduled

On 08.10.2026, from 13:00 to 16:00 (MSK), monthly maintenance work will be carried out on diesel generator unit No. 8 (hereinafter referred to as DG‑8), located at the following address: Ryabinovaya St., 53, building 4 (DATAPRO LLC data center). During the work, DG‑8 will be taken out of automatic start‑up mode, followed by testing at idle and under load. During the work period, the power supply to the MRV‑8 switchboard, from which input No. 1 of the ShchBP‑2.1 (a block of sockets/PDUs marked as ShchBP 2.1, input No. 1) is powered, will be provided via the city power grid through an uninterruptible power supply (hereinafter referred to as UPS No. 8). The autonomous operation time of UPS No. 8 is 41 minutes, and the time required to restore the normal operation of the DGU‑8 is 5 minutes.
At the same time, input No. 2 of machine room No. 2 (a block of sockets/PDUs marked as input No. 2 of the ShchBP-2.2) will operate in normal mode.
These works do not imply a service interruption, only a reduction in redundancy.