Scheduled maintenance on network hardware at the data center Dubrovka-2 from 27-10-25 13:37 MSK

Scheduled maintenance Bare Metal Pools SPB-5 Data centers Infrastructure N+
27-10-25 13:37 MSK · 2 weeks, 4 days, 1 hour, 18 minutes

Updates

Scheduled

Network equipment maintenance is scheduled for October 31, 2025, from 12:00 AM to 5:00 AM Moscow time.

Expected Impact:

  • Redundancy level will be reduced to N+0;
  • Equipment may be unavailable for up to 1 minute.
    We apologize for any inconvenience.
October 27, 2025 · 13:37 MSK