Scheduled work on electrical equipment "Tsvetochnaya-2" from 23-07-25 10:00 MSK to 23-07-25 13:00 MSK

Scheduled maintenance Bare Metal Pools SPB-2 Services Racks
23-07-25 10:00 MSK · 3 hours

Updates

Scheduled

Scheduled electrical equipment upgrades will be carried out in the Tsvetochnaya-2 data center. On July 23, 2025, from 10:00 to 13:00 (UTC/GMT+3), one power input (input A) will be disconnected in some server racks, which will reduce the redundancy level to N+0. We recommend checking:

  • equipment with 1 power supply is connected via ATS;
  • equipment with two power supplies is connected from power supply units (PDU) of different inputs.

If the recommendations are followed, the work will not affect equipment with one power supply.
If the server has two power supplies, one of them will be disconnected, while the equipment will continue to work.

July 18, 2025 · 12:11 MSK