Scheduled maintenance work on network equipment in KZ-1 and ALM-1 (05/20/2025) from 20-05-25 22:00 MSK to 21-05-25 04:00 MSK

Scheduled maintenance Bare Metal Pools ALM-1 Services Dedicated Servers Network Cloud Platform Pools kz-1a Services Network VMware Cloud Services Network Network Services Global router (L3VPN) Data centers Infrastructure Network N+
20-05-25 22:00 MSK · 6 hours

Updates

Scheduled

We inform you about the planned work on the routers of the regions kz-1 and alm-1, May 20 - May 21, 2025. The work will be carried out in the time range from 22:00 to 04:00 (GMT + 3).
The work will affect the external network and the “Global Router” service.
Expected impact on the Internet plane:

  • reducing the level of router redundancy for the entire duration of work to N+0, for all subnets;
  • 2 interruptions are expected, up to 10 seconds each for all subnets including public routers.

Impact on the global router (L3VPN) to other pools and within the region:

  • reducing the level of router redundancy for the entire duration of work to N+0, for all subnets.
May 15, 2025 · 11:55 MSK