Плановое отключение второго ввода в Дубровке-1 from 03-02-25 00:00 MSK to 27-02-25 23:59 MSK

Scheduled maintenance Bare Metal Pools SPB-4
03-02-25 00:00 MSK · 3 weeks, 3 days, 23 hours, 59 minutes

Updates

Scheduled

Dear Customer,
In order to improve the quality of our services, we would like to inform you that scheduled maintenance and upgrades of electrical equipment will be carried out at the Dubrovka-1 data center from 03.02.2025 to 27.02.2025.
As a result, one power supply feed will be temporarily disconnected, which will reduce the level of power redundancy in the server racks.
Servers with a single power supply unit will not be affected by these works.
For servers with dual power supply units, one of the power feeds will be disconnected, but the equipment will continue to operate normally.
We apologize for any inconvenience this may cause.
Thank you for your understanding.

January 29, 2025 · 13:11 MSK