Scheduled Maintenance on Electrical Equipment at Data Center "Tsvetochnaya-2" from 20-11-24 11:00 MSK to 20-11-24 12:00 MSK

Scheduled maintenance Bare Metal Pools SPB-2
20-11-24 11:00 MSK · 1 hour

Updates

Scheduled

On the Tsvetochnaya-2 data center, testing of the AVR system is planned on November 20, 2024, from 11:00 to 12:00.
During the work, supply lines will be disconnected one by one from the city.

Work plan:

  • November 20, 2024 from 11:00 to 11:30 - checking the implementation of the automatic transfer switch when input No. 2 is disconnected;
  • November 20, 2024 from 11:30 to 12:00- checking the implementation of ATS when input No. 1 is disconnected.

During switchovers, the technological equipment of server rooms 2.1, 4.1, 4.2, 4.3 will be powered by their own UPS. Server equipment shutdown is not expected.

If work affects your equipment, you will receive a message through the Notification Center in the Control Panel.
We apologize for any inconvenience this may cause.

November 14, 2024 · 14:53 MSK