Scheduled maintenance work at the Berzarina data center, 06.11.2024 from 06-11-24 10:00 MSK to 06-11-24 17:00 MSK

Scheduled maintenance Bare Metal Pools MSK-1 Services Dedicated Servers Cloud Platform Pools ru-2a Data centers Moscow Berzarina-1 Infrastructure N+
06-11-24 10:00 MSK · 7 hours

Updates

Scheduled

In the period from 10:00 to 17:00 06.11.2024 (GMT+3), during the planned maintenance one of the power inputs of the locations (ru-2,ru-7) will be disconnected, while the other power input will be guaranteed to operate in normal mode.
Expected impact: temporary reduction of the redundancy level to N+0.

No shutdown of server equipment is planned.
We apologize for any inconvenience.