Planned work to modernize the infrastructure of the Cloud platform in ru-3b from 03-10-24 22:00 MSK to 04-10-24 08:00 MSK

Scheduled maintenance Cloud Platform Pools ru-3b Services Cloud servers Network
03-10-24 22:00 MSK · 10 hours

Updates

Update

Due to unexpected technical difficulties that arose during the work, we are forced to extend the scheduled work until 2024-10-04 08:00.

We apologize for the delay. We are doing everything possible to complete the work as soon as possible.

October 4, 2024 · 00:42 MSK
Scheduled

10/03/2024 from 22:00 to 10/04/2024 03:00 Moscow time, planned infrastructure modernization work will be carried out in the ru-3b pool.
During the work, virtual machines will be temporarily unavailable, as cold migration with shutdown will occur.

If this work affects your equipment, you will receive a notification in the control panel.

September 30, 2024 · 11:55 MSK