Planned work to modernize the infrastructure of the Cloud platform in ru-3b from 03-10-24 22:00 MSK to 04-10-24 08:00 MSK
Scheduled maintenance
Cloud Platform
Pools
ru-3b
Services
Cloud servers
Network
03-10-24 22:00 MSK
· 10 hours
Updates
Update
October 4, 2024 · 00:42 MSK
Due to unexpected technical difficulties that arose during the work, we are forced to extend the scheduled work until 2024-10-04 08:00.
We apologize for the delay. We are doing everything possible to complete the work as soon as possible.
Scheduled
September 30, 2024 · 11:55 MSK
10/03/2024 from 22:00 to 10/04/2024 03:00 Moscow time, planned infrastructure modernization work will be carried out in the ru-3b pool.
During the work, virtual machines will be temporarily unavailable, as cold migration with shutdown will occur.
If this work affects your equipment, you will receive a notification in the control panel.
← Back