Scheduled work on modernization of electrical equipment in the data center "Tsvetochnaya-1" from 26-09-24 08:00 MSK to 26-09-24 18:00 MSK
Scheduled maintenance
Data centers
St.Petersburg
Tsvetochnaya-1
Infrastructure
Electricity
26-09-24 08:00 MSK
· 10 hours
Updates
Scheduled
September 24, 2024 · 15:20 MSK
From 08:00 26.09.24 to 18:00, scheduled work to upgrade electrical equipment will be carried out in the Tsvetochnaya-1 data center.
During the work, one power supply input will be disconnected, which will lead to a decrease in the level of redundancy.
The changes will not affect the operation of the server equipment.