Planned work on the modernization of server equipment in SPB-1 from 03-10-24 00:00 MSK to 03-10-24 07:00 MSK
Scheduled maintenance
Bare Metal
Pools
SPB-1
Services
Dedicated Servers
Data centers
St.Petersburg
Tsvetochnaya-1
03-10-24 00:00 MSK
· 7 hours
Updates
Scheduled
September 24, 2024 · 12:56 MSK
In order to improve the quality of our services, on 10/03/2024, from 00:00 to 07:00 Moscow time, planned work will be carried out aimed at modernizing the infrastructure.
In this regard, your server will need to be disconnected from the power supply for up to 2.5 hours, after which server operation will be restored.
If this work affects your equipment, you will receive a notification in the control panel.