Scheduled work on electrical equipment in the Dubrovka-2 data center from 06-08-24 09:30 MSK to 06-08-24 18:00 MSK
Scheduled maintenance
Bare Metal
Pools
SPB-5
06-08-24 09:30 MSK
· 8 hours, 30 minutes
Updates
Scheduled
July 31, 2024 · 10:16 MSK
Scheduled electrical equipment upgrades will be carried out in the Dubrovka-2 data center.
On 06/08/24, from 06:30 to 10:00, one power input will be disconnected, from 11:00 to 15:00, input 2 will be disconnected, which will result in a reduction in the backup level, all times are Greenwich Mean Time.
These works will not affect the operation of servers with one power supply. If the server has two power supplies, one of them will be disconnected, but the equipment will continue to operate.
If the works affect equipment used on the account, an up-to-date list will appear in the notification center.
← Back