Planned works in locations SPB-4 and SPB-5 from 01-08-24 13:00 MSK to 01-08-24 20:00 MSK
Scheduled maintenance
Bare Metal
Pools
SPB-4
SPB-5
Services
Dedicated Servers
Colocation
Cloud Platform
Services
Cloud servers
Object Storage
VMware Cloud
Pools
AVM1 + BRZ2 | PLATINUM-1
DUB3 | SILVER-1
DUB3 | GOLD-1
DUB3 + CVT2 | GOLD-1
Data centers
St.Petersburg
Dubrovka-2
Dubrovka-3
VDS by Selectel
Moscow
01-08-24 13:00 MSK
· 7 hours
Updates
Scheduled
July 30, 2024 · 19:00 MSK
In the data center “Dubrovka-2” and “Dubrovka-3” from 13:00 to 20:00 it is planned to carry out routine maintenance of equipment at the distribution substation.
In connection with this, power supply redundancy will be reduced, equipment shutdown is not expected.
← Back