Scheduled work on electrical equipment (Berzarina-1) from 14-08-24 21:00 MSK to 15-08-24 06:00 MSK

Scheduled maintenance Bare Metal Pools MSK-1 Data centers Moscow Berzarina-1 Infrastructure Electricity
14-08-24 21:00 MSK · 9 hours

Updates

Scheduled

In the data center “Berzarina-1” scheduled work on the modernization of electrical equipment will be carried out.

From 14.08.2024 to 15.08.2024, in the period from 21:00 to 06:00 (UTC/GMT+3), one power supply input will be turned off in some server racks, which will lead to a decrease in the level of redundancy.

These operations will not affect the operation of servers with one power supply unit, if the server has two power supplies, then one of them will be turned off, while the equipment will continue to work.

If work impacts equipment used on the account, an up-to-date list will appear in the notification center.