Planned work on power supply to the racks of the Berzarina DC 07/19/2024 from 19-07-24 10:00 MSK to 19-07-24 11:00 MSK

Scheduled maintenance Bare Metal Pools MSK-1 Data centers Moscow Berzarina-1 Infrastructure Electricity
19-07-24 10:00 MSK · 1 hour

Updates

Scheduled

07/19/2024 During the period from 10:00 to 11:00 Moscow time, during scheduled work, one of the power inputs to the racks where your rental equipment is located will be turned off. In this case, the other power input will be guaranteed to operate normally.

Expected impact:

  • reduction of power supply redundancy level to N+0

Disabling server equipment is not expected.
Please apologize for the inconvenience.