Scheduled maintenance work on power supply devices - SPB-4, SPB-5 07/03/2024 from 03-07-24 01:00 MSK to 03-07-24 05:00 MSK
Scheduled maintenance
Bare Metal
Pools
SPB-4
SPB-5
Data centers
Infrastructure
Electricity
N+
03-07-24 01:00 MSK
· 4 hours
Updates
Scheduled
June 27, 2024 · 17:08 MSK
In the period from 07/03/2024 01:00 to 07/03/2024 05:00 Moscow time, scheduled maintenance of power supply devices in pools SPB-4 and SPB-5 will be carried out.
During the work, the level of power supply redundancy will be reduced.
If your equipment falls under the specified work, you will receive a corresponding notification in the my.selectel.ru control panel.