06-03-25 MSK
Planned infrastructure modernization works 03/06/25 , Dubrovka-3 from 06-03-25 23:00 MSK to 07-03-25 02:30 MSK
05-03-25 MSK
The problem with the availability of the ru-3 region
04-03-25 MSK
Problems with the Control Panel in the ke-1 pool
04-03-25 MSK
Problem with attaching domains in the Selectel email service
03-03-25 MSK
Scheduled work ru-7, 02.27.2025 from 03-03-25 22:00 MSK to 04-03-25 00:00 MSK
03-03-25 MSK
Planned work to modernize the infrastructure in the Dubrovka-1 data center from 03-03-25 09:00 MSK to 28-03-25 18:00 MSK
03-03-25 MSK
Scheduled maintenance on the cloud platform ru-2c from 03-03-25 07:30 MSK to 03-03-25 09:30 MSK
28-02-25 MSK
Network unavailability in DC Dubrovka-2
28-02-25 MSK
Planned infrastructure upgrade work at the "Dubrovka-1" data center (SPB-4) from 28-02-25 00:00 MSK to 28-02-25 08:00 MSK
27-02-25 MSK
Scheduled maintenance on the VMware public cloud infrastructure MSK from 27-02-25 00:00 MSK to 27-02-25 04:00 MSK
26-02-25 MSK
Planned work to modernize the network infrastructure in the Dubrovka data center SPB-4 from 26-02-25 23:00 MSK to 26-02-25 23:59 MSK
26-02-25 MSK
Problems in the work of the manager of secrets
26-02-25 MSK
Planned Infrastructure Upgrade in the Tsvetochnaya-2 from 26-02-25 00:00 MSK to 26-02-25 04:00 MSK
25-02-25 MSK
The problem with creating cloud routers in the ke-1 region, Nairobi
25-02-25 MSK
Scheduled maintenance of Cloud platform hosts in ru-3b from 25-02-25 07:30 MSK to 25-02-25 09:30 MSK
24-02-25 MSK
Scheduled work to upgrade the power supply chain in the Berzarina-1 from 24-02-25 08:00 MSK to 24-02-25 20:00 MSK
24-02-25 MSK
Scheduled maintenance on the Cloud platform from 24-02-25 05:00 MSK to 24-02-25 08:00 MSK
21-02-25 MSK
The problem is with the control panel
21-02-25 MSK
Scheduled maintenance of Cloud platform hosts in ru-2c from 21-02-25 07:00 MSK to 21-02-25 10:30 MSK
20-02-25 MSK
Scheduled maintenance to improve the infrastructure of the SPB-3 from 20-02-25 23:00 MSK to 21-02-25 02:00 MSK
20-02-25 MSK
Scheduled work on network equipment at the TAS-2 location, 02/21/25 from 20-02-25 22:00 MSK to 21-02-25 02:00 MSK
19-02-25 MSK
Problems with the operation of resources in the 1C cloud
19-02-25 MSK
Scheduled infrastructure upgrade works in data center Tsvetochnaya-2 from 19-02-25 00:00 MSK to 19-02-25 04:00 MSK
18-02-25 MSK
Problems with the ticket system when generating a response
17-02-25 MSK
Planned work to modernize the network infrastructure in the Dubrovka data center SPB-4 from 17-02-25 23:00 MSK to 18-02-25 02:00 MSK
17-02-25 MSK
Planned work in the Cloud platform, affecting Managed Databases, Ready Cloud 1C and Managed Kubernetes from 17-02-25 21:00 MSK to 17-02-25 23:00 MSK
17-02-25 MSK
Scheduled maintenance of Cloud platform hosts in ru-3b from 17-02-25 07:00 MSK to 17-02-25 10:30 MSK
13-02-25 MSK
Scheduled maintenance work on Cloud Platform hosts in ru-9a from 13-02-25 20:00 MSK to 13-02-25 23:00 MSK
13-02-25 MSK
Problems with displaying cloud database monitoring
13-02-25 MSK
Problems with accessibility of my.selectel control panel
13-02-25 MSK
Scheduled maintenance on the Cloud Platform infrastructure from 13-02-25 06:00 MSK to 13-02-25 08:00 MSK
12-02-25 MSK
Problems on the fiber-optic communication line Berzarina-M9
12-02-25 MSK
Scheduled infrastructure upgrade work in the Dubrovka-1 SPB-4 data center from 12-02-25 00:00 MSK to 12-02-25 08:00 MSK
12-02-25 MSK
Planned infrastructure modernization works at the Tsvetochnaya-2 data center from 12-02-25 00:00 MSK to 12-02-25 04:00 MSK
11-02-25 MSK
Scheduled work on the public cloud infrastructure based on VMware in the MSK from 11-02-25 22:00 MSK to 12-02-25 06:00 MSK
11-02-25 MSK
Scheduled work on network equipment Dubrovka-2 from 11-02-25 14:00 MSK to 11-02-25 15:00 MSK
11-02-25 MSK
Problem in the operation of the SPB-3 LAN segment
11-02-25 MSK
Emergency work in SPB-4, Dubrovka-1 from 11-02-25 00:00 MSK to 11-02-25 03:00 MSK
10-02-25 MSK
Planned infrastructure modernization works at the SPB-3 Dubrovka-3 location from 10-02-25 23:00 MSK to 11-02-25 00:00 MSK
10-02-25 MSK
Partial unavailability of resources in uz-1
06-02-25 MSK
Scheduled maintenance on the data center infrastructure SPB-4 from 06-02-25 23:00 MSK to 07-02-25 03:00 MSK
06-02-25 MSK
Scheduled maintenance on the power supply network of DC Berzarina from 06-02-25 23:00 MSK to 07-02-25 07:00 MSK
06-02-25 MSK
Scheduled maintenance work for Cloud Platform in ru-9a from 06-02-25 21:00 MSK to 07-02-25 03:00 MSK
06-02-25 MSK
Scheduled maintenance work on the network infrastructure of the Cloud Platform in the ru-2 pool from 06-02-25 18:00 MSK to 06-02-25 20:00 MSK
06-02-25 MSK
Emergency maintenance on infrastructure modernization in the data center "Dubrovka-1" from 06-02-25 00:00 MSK to 06-02-25 08:00 MSK
05-02-25 MSK
Scheduled maintenance on the power supply network of DC Berzarina from 05-02-25 23:00 MSK to 06-02-25 07:00 MSK
04-02-25 MSK
Scheduled maintenance on the power supply network of DC Berzarina from 04-02-25 23:00 MSK to 05-02-25 07:00 MSK
04-02-25 MSK
Scheduled work on upgrading server equipment in SPB-2 from 04-02-25 00:00 MSK to 04-02-25 07:00 MSK
03-02-25 MSK
Planned work to modernize the network infrastructure in ru-3 from 03-02-25 18:00 MSK to 03-02-25 20:00 MSK
03-02-25 MSK
Плановое отключение второго ввода в Дубровке-1 from 03-02-25 00:00 MSK to 27-02-25 23:59 MSK